The replacement cost gap

A new 20,000 SF warehouse in Hialeah costs $380 to $430 per square foot to deliver. Existing warehouses in the same submarket traded this quarter at $152 to $287. That gap is the most important number in Miami industrial right now, and most owners have not run it on their own building.

Every input to new construction has moved against the developer since 2020. Copper is up about 150%, aluminum about 95%, and cement and concrete about 45%, against roughly 30% for consumer inflation over the same period. Industrial land in Hialeah is trading at $65 to $80 per square foot. Labor costs more. And the construction loan that carried a near-zero rate in 2020 now has an interest cost that shows up as a significant line item in the budget.

 

What it costs to build a 20,000 SF box in Hialeah today

$380 to $430 a square foot, all-in, before the developer makes a dollar. Here is the stack for a 20,000 SF block building on one acre.

The shell number comes from Rider Levett Bucknall, which publishes $80 to $160 a square foot for Miami warehouses in its Q3 2026 cost report. The $80 end is a 300,000 SF box out west where the concrete truck has room to turn around. In Hialeah the concrete truck is blocking somebody’s driveway. Add the High-Velocity Hurricane Zone code on top and $160 is the honest number for a small building here.

Land is the line that surprises people. At $65 to $80 a foot, the dirt alone is $142 to $174 per square foot of building before anyone pours a slab. Five years ago a developer paid about $23 a square foot for 5.8 acres of industrial land in unincorporated Hialeah. That number is now a story old brokers tell.

The rent it would take versus the rent the market pays

A new 20,000 SF box needs $27 to $30 NNN to pencil. The market pays $16 to $20.

The math is not complicated. At $380 to $430 a foot all-in, a 7% yield on cost needs $26.60 to $30.10 in net rent, and that is break-even, not profit. A 20,000 SF dry warehouse in Hialeah leases today for $16 to $20 NNN. The best building in the submarket is $7 to $14 a foot short of what a new one needs.

That is why nobody is putting up a spec warehouse in Hialeah right now. The rents are not there, the land is not there, and the bank’s spreadsheet says the same thing mine does.

What existing Hialeah warehouses actually traded for

Four Hialeah warehouses sold in August at $152 to $287 a square foot. Every one of them cost less to buy than it would cost to rebuild on its own lot.

These buyers paid $113 to $212 per square foot of dirt, which is more than a developer would pay for vacant dirt. They also got a building. A 40 to 70-year-old building, sure, but it has a roof, a tenant, and a certificate of occupancy, which puts it about two years ahead of anything you could start today.

Take the 1962 block buildings on E 10th Ct. Rebuilding 29,890 SF on that lot at today’s numbers runs about $7.5 million to $8.5 million. They sold for $4.5 million. Obsolete is a word developers use for buildings they do not own.

What this means for owners, tenants, and buyers

If you own one. Congratulations, you own a hedge. The 1960s block building a developer called obsolete five years ago now costs more to replace than it would sell for. The building did not get better. Replacing it got expensive. And your competition is not new supply, because there is none coming at these numbers.

If you lease one. Copper is electrical. If you need heavy power, A/C, or a service upgrade for cold storage or manufacturing, the quote you get today will not look like the one your landlord got in 2021. The guy with the raw box next door is about to find out what a 1,200-amp service costs now, and it is going to ruin his week. Buildings that already have power, sprinklers, and dock height carry a premium. Expect landlords to push more of the buildout onto tenants, and expect to trade a longer lease for a landlord who funds it.

If you are buying one. Stop underwriting value-add on 2021 TI numbers. 2021 is over. It was over in 2022. The spread between a raw box and a built-out one is wider than it was and still widening. Buy the building that already has the expensive stuff in it. Paying $250 a foot for a building with 1,200 amps, ESFR sprinklers, and 24-foot clear is cheaper than paying $150 for one without and then adding it. Ask anyone who has tried.

The caveat

I am not telling you it is a boom. Expensive construction limits supply. It does not create demand. Nobody signs a lease because concrete got pricey. If tenant demand cools, developers do not build, land sits, and prices hold while deal volume drops. That is a slower market, not a falling one.

Higher rates cut both ways too. They stop the developer from building, and they cap what a leveraged buyer can pay for your building. The replacement cost gap holds values up. It does not conjure a buyer at your number. Fewer deals, not necessarily lower prices. It rewards the buyer who picks the right building over the one still waiting for the right moment.

What to do with this

Property tax bills arrived last week week. If that is the only time all year you think about what your warehouse is worth, run the numbers above on your own building. Your replacement cost went up a lot more than your tax bill did, and your tax bill went up plenty.

Every warehouse trade across our Miami industrial coverage is in our interactive subwarehouse reports at builtworldadvisors.com/market-research. Filter by year, click any sale on the map, see the full deal history behind it. If someone has been telling you what your building is worth without showing you the comps, spend ten minutes there first. It is free, and it is faster than arguing.